AI infrastructure
An AI megawatt is not a megawatt
With external IT at 10% of rack power, an IT gigawatt fits 460,948 modeled B300 GPUs because building overhead sits outside that budget, leaving more electricity for racks than a facility gigawatt would. The starting point matters. I’d identify it before converting a megawatt claim into a fleet.
The modeled facility fits 402,574 B300 GPUs. Its power date, workload, and customer contract decide what that equipment is worth.

A one-gigawatt facility converts to 402,574 modeled B300 GPUs under this model. I would value it on the power it can use on time, the workload it can preserve, and the service someone has agreed to buy.
The model holds the hardware constant at GB300 NVL72 racks and allocates the facility’s electricity between building systems, rack equipment, and the IT outside each rack. A grid request starts much earlier in that chain: its gigawatt can describe a future connection without an installed fleet.
The conversion is reproducible. The investment needs another chain of evidence, from an energized phase to functioning machines, preserved work, and paid service.
Method & limits
This homogeneous GB300 model uses the original engineering scenarios and October 22, 2026 calculator. The 142 kW rack requirement is an “up to” specification. PUE and external-IT allowances are scenario inputs. Annual PUE allocates the nameplate budget; coincident peak loads need a measurement. NVIDIA’s whole-rack specification and Google goodput research were checked October 25, 2026. The blocked LBNL landing-page body, historical project inputs, and Texas site status weren’t refreshed. TPU results provide a measurement framework; the GB300 efficiency factor remains unmeasured. The model estimates conditional equipment and GPU-hours. A project’s dated operating and financial record would have to supply its installed-fleet or revenue claim.
A grid request starts before a facility nameplate
A grid request concerns the connection point and its margins. Facility nameplate covers the building, including cooling, power conversion, and lighting. IT nameplate covers servers and supporting IT; rack nameplate draws a tighter circle around the cabinet. Average demand measures the flow over time. Each can be quoted in megawatts while describing a different purchase.
LBNL says conversions among annual energy, average and maximum demand, facility nameplate, and requested connection capacity need project-specific relationships. Its illustrative interconnection utilization is about 50%, allowing for redundancy and maintenance, with the value described as poorly documented. I would use the project’s own design and power agreement before converting a request into equipment. LBNL definitions.
I need the statement’s connection point, operating state, and time basis before calculating a GPU count. Requested power and occupied halls can both describe a real project at different dates. The interval between them is time when capital is committed and the proposed service is still waiting.
| Term | Power reference or state | What can be calculated | What remains unknown |
|---|---|---|---|
| Announced program capacity | Corporate plan; may combine sites and phases | Nothing mechanical without further disclosure | Site, timing, metering, firmness, equipment |
| Requested interconnection | Maximum requested at grid point, including margins | Illustrative annual energy if average utilization is assumed | Firmness, energization, facility design, installed fleet |
| Firm / energized interconnection | Contracted or physically available grid capacity | Upper electrical envelope at the stated meter | Average draw, PUE, occupancy, rack mix |
| Facility nameplate | Whole-building maximum electrical capacity | IT capacity after PUE; rack capacity after external IT allowance | Actual average draw and utilization |
| IT nameplate | Servers, network, storage, and support IT | Rack capacity after external IT allowance | Facility draw unless PUE is known |
| Compute-rack nameplate | GB300 rack “up to” requirements | Rack and installed-GPU equivalents | Actual workload draw and useful work |
| Average facility demand | Time-weighted facility power | Annual MWh/TWh | Installed fleet without nameplate and utilization |
| Full-load-equivalent compute | Installed fleet × computational utilization × time | Comparable accelerator-hours within a defined generation | Useful work, service quality, and revenue |
The calculator follows the power into the rack
The calculator and workbook use NVIDIA’s whole-rack requirement of up to 142 kW for 72 B300 GPUs. The examples scale 1, 10, 100, and 1,000 MW at the selected electrical point. I use the conversion to compare assumptions about equipment that could fit. NVIDIA’s rack specification supplies the denominator.
Facility nameplate divides by PUE once; IT nameplate skips that division. A 10% external-IT allowance divides the IT budget by 1.10 because it adds to rack power. Whole racks round down from the workbook’s rack equivalents. Computational utilization changes annual GPU-hours while the installed rack count stays fixed.
GB300 NVL72 · 72 GPUs per rack · up to 142 kW
Change assumptionsPUE 1.145 · external IT 10% · utilization 80%
- Rack-equivalent GPUs
- 402,574
- Whole racks that fit
- 5,591
- GPUs in those whole racks
- 402,552
5,591.31 rack equivalents × 72 × 8,760 × 80% = 2,821.24 million full-load-equivalent GPU-hours/year.
Overhead sensitivity at the selected capacity
| Scenario | PUE | External IT | GPU equivalents |
|---|---|---|---|
| Efficient | 1.1 | 6% | 434,856 |
| Reference | 1.145 | 10% | 402,574 |
| Conservative | 1.25 | 14% | 355,819 |
Capacity allocation, not an installation certificate. Fractional rack equivalents reproduce the workbook; a whole-rack deployment rounds down. PUE is an energy ratio, not a measured coincident peak-power ratio. GPU-hours measure computational intensity, not paid utilization or useful work.
Once the physical capacity is bounded, follow the data-center financing waterfall from construction and power delivery to customer acceptance, debt service and the cash left for equity.
Facility power funds IT, then racks
I start with 1,000 MW of total facility nameplate, then use PUE to allocate IT power and an external-IT factor to reserve the network, storage, support servers, and management outside the racks.
Holding every rack at GB300 NVL72 isolates the electrical conversion. A campus mixing accelerators, CPUs, generations, spares, and partially occupied halls needs its own equipment inventory.
The order matters. Dividing facility power by PUE pays for building overhead. Reserving the IT outside the rack pays for supporting equipment. The remaining power buys rack equivalents. Charging building overhead again would shrink the modeled fleet twice.
PUE is an energy ratio measured over a period. Peak electrical and cooling design also needs its load point, weather, redundancy, and power caps. I would keep the annual allocation calculation beside the project’s electrical one-line, cooling design, and vendor configuration. Those documents determine whether the counted machines can run together under the chosen policy.
An annual average can coexist with a more demanding peak. I would require the installation design to support the operating policy before assigning value to every modeled GPU.
| Step | Formula | Reference input | Reference output |
|---|---|---|---|
| Facility → IT | IT MW = facility MW ÷ PUE | 1,000 MW ÷ 1.145 | 873.36 MW |
| IT → compute racks | Rack MW = IT MW ÷ (1 + external IT overhead) | 873.36 MW ÷ 1.10 | 793.97 MW |
| Rack MW → racks | Racks = rack MW × 1,000 ÷ 142 kW | 793.97 MW | 5,591.31 rack equivalents |
| Racks → GPUs | GPUs = racks × 72 | 5,591.31 × 72 | 402,574 B300 GPUs |
| Fleet → FLE hours | FLE = GPUs × 8,760 × utilization | 80% training utilization | 2.82B GPU-hours/year |
The whole rack needs up to 142 kW
One liquid-cooled GB300 NVL72 rack contains 18 compute trays, 72 B300 GPUs, and 36 Grace CPUs, with a requirement of up to 142 kW. Each tray includes ConnectX-8 adapters, a BlueField DPU, boot storage, and local cache alongside four GPUs and two CPUs. NVIDIA’s rack and tray specifications count the equipment inside that cabinet.
I start with rack power because per-GPU thermal design power leaves out CPUs, memory, NVLink, storage, adapters, management hardware, and internal conversion losses. Those components draw from the same electricity budget.
The “up to” requirement sizes this rack-count exercise. Annual energy needs the workload’s power profile. I would credit lower average draw as additional installed capacity only when the electrical design supports that policy, rather than also claiming the same reduction as an energy saving.
| Element | Quantity | Power or role | Treatment |
|---|---|---|---|
| GB300 rack / scalable unit | 1 | Up to 142 kW | Compute-rack nameplate denominator |
| Compute trays | 18 | 4 B300 + 2 Grace per tray | Node count and equipment included in the system |
| B300 GPUs | 72 | Accelerators in one NVLink domain | Installed fleet output |
| Grace CPUs | 36 | Host compute and memory | Included inside rack nameplate |
| In-rack management switches | 2 SN2201 | OOB access; DC busbar | Included inside rack specification |
| External fabrics | Compute, converged, storage/customer, support, OOB | Scale-out and operations | Reserved in external-IT overhead |
Eight racks leave the campus network unresolved
NVIDIA’s eight-rack bill of materials totals 576 GPUs, 44 compute-core switches, 11 converged-core switches, and 16 out-of-band management switches. The lower-input case uses SN5600 switches at 940 W and gives 53.27 kW, or 4.69% of the racks’ combined 1.136 MW nameplate, before storage, support servers, customer-edge equipment, or further tiers. The bill of materials, SN5000 power specifications, and SN2201 specification let you reconstruct that floor.
The bill of materials and logical architecture name SN5600, while the hardware page names SN5610. The latter specifies 900 W with passive cables and 2.08 kW with 64 optical modules. Using that optical comparator for 55 high-speed switches raises the total to 115.97 kW, or 10.21% of rack nameplate. I treat that as a comparison of optics assumptions, with each model named in the BOM, hardware page, and specification.
The campus fleet has roughly 100,000 compute trays, far beyond the eight-rack design point. NVIDIA introduces a super-spine around 1,024 nodes and divides fabrics in larger designs. I would price the scale-out, storage, customer, support, and management networks for the proposed campus instead of multiplying the small design unchanged. Scaling architecture.
I test external-IT allowances of 6%, 10%, and 14%. Six percent clears the passive-switch floor; ten approaches the optical comparator before unquantified support equipment. Fourteen comes from a GB200-era Epoch IT/server decomposition, which checks magnitude across generations. The table preserves the underlying switch reconstruction.
| Component | Count | Lower typical power | Optical comparator | Notes |
|---|---|---|---|---|
| Compute-core high-speed switches | 44 | 41.36 kW | 91.52 kW | BOM says SN5600; comparator uses SN5610 with 64 optical modules |
| Converged-core high-speed switches | 11 | 10.34 kW | 22.88 kW | Same model-name contradiction |
| OOB switches | 16 | 1.57 kW | 1.57 kW | SN2201 at 98 W typical |
| Total external switches | 71 | 53.27 kW | 115.97 kW | Excludes support servers, storage, super-spine, and facility infrastructure |
| Share of eight-rack nameplate | 8 × 142 kW | 4.69% | 10.21% | Denominator is compute-rack nameplate |
The facility reference yields 402,574 B300 GPUs
I get 402,574 installed modeled B300 GPUs from the facility reference: divide by PUE, reserve external IT, and convert the rack power at NVIDIA’s requirement. The table gives each intermediate result. LBNL’s 1.145 PUE describes its estimated 2024 average for AI facilities; NVIDIA supplies the rack specification and LBNL supplies that energy-ratio input.
The efficient and conservative assumptions span 434,856 to 355,819 GPU equivalents. Their 79,037-GPU gap is about 1,098 racks. I use that spread to compare the overhead assumptions; the scenarios assign no probabilities.
The wrong electrical starting point can overwhelm that sensitivity. A grid request leaves equipment unknown. Dividing an IT figure by PUE charges for building overhead a second time.
| Scenario | PUE | External IT overhead | IT MW | GB300 rack MW | Rack equivalents | Installed B300 GPUs |
|---|---|---|---|---|---|---|
| Efficient | 1.1 | 6% | 909.09 | 857.63 | 6,040 | 434,856 |
| Reference | 1.145 | 10% | 873.36 | 793.97 | 5,591 | 402,574 |
| Conservative | 1.25 | 14% | 800.00 | 701.75 | 4,942 | 355,819 |
An IT gigawatt fits more GPUs than a facility gigawatt
Epoch’s gigawatt cost model begins with IT nameplate and applies PUE and utilization for operating energy. A 10% external-IT allowance then leaves 909.09 MW for racks and supports 460,948 modeled B300 GPUs, roughly 58,000 more than my facility case. Building overhead sits outside that gigawatt. Epoch’s model.
A one-gigawatt grid request yields no installed-fleet estimate. LBNL’s illustrative 50% utilization gives 500 MW of average facility draw and 4.38 TWh per year. Facility nameplate could still be 1 GW, 700 MW, 500 MW, or phased halls, with PUE, IT mix, density, and occupancy to determine. LBNL’s definitions.
A campus can be real without being complete. Epoch’s hub describes phased openings and uncertain incremental timelines. I would put requested, energized, commissioned, and occupied power on the project’s schedule, then price the capital needed to carry each interval. The full-build power number leaves the revenue start date open.
| What 1 GW means | Immediate implication | Reference arithmetic | Installed GPU inference |
|---|---|---|---|
| Total facility nameplate | Whole-building maximum capacity | 873.36 IT MW after PUE | ≈ 402,574 GPUs with 10% external IT overhead |
| IT nameplate | Servers + external network/storage/support IT | 909.09 compute-rack MW after 10% allowance | ≈ 460,948 GPUs |
| Interconnection request | Maximum requested at grid point, including margins | 500 MW average and 4.38 TWh/year at 50% | Not identifiable from the request alone |
| Average facility draw | Time-weighted whole-building power | 8.76 TWh/year at 1 GW average | Not identifiable without nameplate, PUE, and loading |
Busy accelerators can still waste work
Powering the reference fleet for a year counts 3.53 billion GPU-hours. The workload determines how much computation and preserved progress those hours buy.
LBNL assumes 80% computational utilization for training, within a 75%–85% range, and 20% for inference by 2030, with a 30% high-inference case. Those factors give the reference fleet 2.64–3.00 billion training full-load-equivalent GPU-hours, 0.705 billion at 20% inference, and 1.06 billion at 30%. I keep those workload cases in the LBNL framework.
The result depends on architecture and hardware generation. Precision, sparsity, and communication change the work behind it. Checkpointing and failed jobs decide how much of that work survives, while software and throttling change its delivery.
Google’s 2025 TPU fleet study distinguishes scheduling availability, runtime progress, and program efficiency. Work since the last saved checkpoint disappears on failure; an optimization can lower hardware utilization while shortening the job. I would measure preserved progress and completion time alongside chip activity. The fleet study supplies that measurement approach for this different hardware.
Idle capacity need not be useless capacity. Google’s earlier technical account recommends reserves and hot spares for availability and recovery. I would judge headroom by the peak or service commitment it protects. Maximizing utilization can remove the slack that makes the service dependable. Goodput and recovery.
A reserved machine can earn a payment while idle. A busy internal machine can earn no external revenue. I would connect equipment to cash through the customer contract, delivery obligations, prices, and service credits.
| Workload case | Computational utilization | FLE B300 GPU-hours/year | Average rated-power fraction at 20% idle |
|---|---|---|---|
| Training low | 75% | 2.645B | 80.0% |
| Training reference | 80% | 2.821B | 84.0% |
| Training high | 85% | 2.998B | 88.0% |
| Inference reference | 20% | 0.705B | 36.0% |
| Inference high | 30% | 1.058B | 44.0% |
The power needs a date and a paid job
I would ask for the phase’s power allocation and date, supported equipment, workload, and paid service obligation. Explicit assumptions make a range assessable. Combining a request, installed equipment, and active computation into one number hides the steps an investment still has to fund.
The time between those steps may matter more than a better overhead factor. Commissioning, scheduling, and recovery can make existing racks productive sooner. The following fields connect the power number to the installation and service behind it.
| Decision | Fields to request |
|---|---|
| Electricity | Connection point; requested, firm, energized, or occupied state; phase dates; peak or annual average |
| Building and IT | PUE value, measurement period, and load point; cooling; network, storage, support, and management allocations |
| Equipment | Accelerator generation, rack architecture, quantity, mix, installation phase, and configuration |
| Workload and resilience | Computational intensity, scheduling availability, paid utilization, redundancy, margins, and recovery |
| Support for the claim | Utility filing, electrical one-line, vendor order, asset register, and management estimate with its date |
Texas has a date problem before it has a GPU count
ERCOT’s July 29, 2026 presentation reports about 474 GW of large-load requests using June data, roughly 90% from data centers. Its April preliminary forecast puts 2032 demand near 367,790 MW and says that planning snapshot exceeds expected growth. I would keep those populations and dates apart: subtracting them would invent spare power. The queue presentation and preliminary forecast describe different planning questions.
I would match equipment delivery to the allocation that can energize for that phase. ERCOT’s September 3 Batch Zero classifications remained conditional on verification and other requirements. The adopted large-load standards took effect October 8, with project treatment dependent on its agreements. The conditional classifications and adopted rule describe the commitment before power becomes usable.
The intermediate agreement requires a $100,000 study fee and $50,000 per requested MW in security. Agreement-stage security becomes the greater of $50,000 per contracted MW or allocated system-upgrade costs, while direct connection costs are nonrefundable construction contributions. Refundable security ties up liquidity; construction contributions spend it. I would credit the intermediate amount when moving to the next stage, as §25.194(d) and (f) require, to avoid charging the security twice.
Energization returns 20% of the remaining security balance, with later returns tied to milestones. A phased schedule missed by 24 months starts a notice and security process for the schedule as a whole. I would price that expensive option alongside the unresolved minimum-billing terms. The checked July proposal for at least 20 years of billing was still a proposal: the adopted interconnection rule assigns those charge details to the billing proceeding.
The archived site example uses 80 MW at 70% average load: 490,560 MWh in a non-leap year. At an assumed $65/MWh, supply costs $31.89 million before delivery and other bill items. A delay at $150,000 a month costs $2.7 million over 18 months. I would fund the wait as well as the eventual electricity bill.
A data-center certification leaves route-specific eligibility to check under the Texas tax rules. A water budget can cover a year and still leave the cooling system short in the week that matters. The water framework leaves that physical delivery question to the facility. I would tie equipment and customer promises to the phase’s usable power and cooling, then calculate its supported fleet.
The count earns its value when the service works
The engineering comparison leaves a named campus’s firm power, cooling envelope, topology, equipment mix, occupancy, and bookings to verify. Storage and support power also remain incompletely quantified outside the eight-rack reconstruction. I would resolve those design inputs before committing the whole installation budget.
I count 402,574 modeled B300 GPUs under the declared facility assumptions. I would value them through the dated installation and workload record, followed by the contract they can serve. A different generation or workload needs its own conversion; those B300 units and GPU-hours cannot be relabeled as H100-equivalents, tokens, training runs, or cash.
Once the power requirement is clear, the financing question begins. Hidden hardware financing compares debt, equipment, and parent-capital claims around physical AI infrastructure.
The power earns its return through the service
I would value the project through the dated commitments that turn power into supported machines and those machines into dependable service. The conditional GPU count sizes the equipment. An energized phase, preserved workload, and paying customer earn the return.
Sources
- System Hardware & Components: NVIDIA NVL72 AI FactoryVerified Aug 16, 2026
- Overview: NVIDIA NVL72 AI FactoryVerified Aug 16, 2026
- Appendix B – Node Configurations: NVIDIA NVL72 AI FactoryVerified Aug 16, 2026
- Network Logical Architecture: NVIDIA NVL72 AI FactoryVerified Aug 16, 2026
- Networking Hardware: NVIDIA NVL72 AI FactoryVerified Aug 16, 2026
- Spectrum-4 SN5000 Switch Systems SpecificationsVerified Aug 16, 2026
- SN2201 and SN2201_M SpecificationsVerified Aug 16, 2026
- United States Data Center Energy Usage Report: 2025 UpdateVerified Aug 16, 2026
- GPUs account for about 40% of power usage in AI data centersVerified Aug 16, 2026
- Total cost of ownership of a one-gigawatt AI data centerVerified Aug 16, 2026
- Introducing the Frontier Data Centers HubVerified Aug 16, 2026
- SB6 legislative history, 89th Regular SessionTexas Legislature Online · 2025-06-20Verified Oct 12, 2026
Governor’s signature and immediate effective date of the enrolled law.
- SB6 enrolled textTexas Legislature Online · 2025-05-30Verified Oct 12, 2026
Final enrolled text. Sections 2, 4, and 6 define scope, interruption mechanisms, co-location, and cost-recovery review.
- Adopted 16 TAC §25.194: Large Load Interconnection StandardsTexas Secretary of State / Public Utility Commission of Texas · 2026-10-02Verified Oct 13, 2026
Filed September 18 and effective October 8, 2026. Applicability and transitions depend on the project and prior agreements.
- ERCOT Senate grid assessmentERCOT · 2026-07-29Verified Oct 12, 2026
Page 6: June 2026 large-load requests. Page 2: existing-generation co-location. Requested power precedes operating demand.
- Preliminary Long-Term Load Forecast, 2026–2032ERCOT · 2026-04-15Verified Oct 12, 2026
ERCOT’s preliminary planning snapshot, expressly distinguished from predicted construction. The article keeps that forecast date.
- Batch Zero verification and audit presentationERCOT · 2026-08-20Verified Oct 12, 2026
Pages 2 and 10 describe the August pause and planned eligibility-verification report. Later September notices supply classifications and RFI issuance.
- M-A080326-04: Batch Zero conditional classificationsERCOT · 2026-09-03Verified Oct 12, 2026
Provisional categories remain subject to verification, model-data corrections, and specified exceptions before energization.
- M-A090926-01: Batch Zero verification RFIERCOT · 2026-09-09Verified Oct 12, 2026
Eligibility RFI with timing measured from issuance to each recipient.
- M-B091426-01: Data Center State and Community Impact RFIERCOT · 2026-09-14Verified Oct 12, 2026
Covered projects, October 12 response deadline, TWDB partnership, and expected December 10 report. This community inquiry differs from eligibility verification.
- Governor’s directive to halt TCEQ data-center permitsOffice of the Texas Governor · 2026-09-21Verified Oct 12, 2026
Directive requesting an October 19 update. Specific permit outcomes and audit completion require their own records.
- Proposed 16 TAC §25.521: Large Load Demand Management ServiceTexas Secretary of State / Public Utility Commission of Texas · 2026-08-14Verified Oct 12, 2026
Proposal filed July 30, 2026; effective commercial terms need a final adoption record.
- 89th Legislative Session: ERCOT implementation status, September 2026ERCOT · 2026-09-15Verified Oct 12, 2026
Cover and index date: September 2026. Pages 10–12 describe demand-management implementation in progress.
- Proposed transmission-cost recovery and large-load tariff rules, Project 58000Texas Secretary of State / Public Utility Commission of Texas · 2026-07-24Verified Oct 13, 2026
Proposed §25.193(d) and §25.252, filed July 9 with August 23 as the earliest possible adoption. October 2’s adopted §25.194 leaves charges to that proceeding. Retrieval was limited; later final treatment and utility tariffs remain unverified.
- Adopted §25.194(g): non-utilized transmission capacityTexas Public Utility Commission / Texas Register · 2026-10-02Verified Oct 16, 2026
Schedule-wide 24-month non-utilization trigger, notice, outstanding amounts, and security returns. The reading covers the rule, leaving project application and final billing terms to check.
- Texas Tax Code Chapter 151, §§151.359 and 151.3595Texas Legislature · Current consolidated law checked October 12, 2026Verified Oct 13, 2026
Under §151.3595(d)(2)(B), the investment period begins at the earlier application or certification date. The exemption begins on certification under subsection (f).
- State sales-tax exemption for qualifying data centers and large projectsTexas Comptroller of Public Accounts · Current agency guidanceVerified Oct 13, 2026
The overview conflicts with the controlling text on the investment clock and large-route state/local claims. Apply §§151.359 and 151.3595 with route-specific Form 01-929.
- 2027 State Water Plan: adoption and proposed amendmentTexas Water Development Board · Phase I adopted 2026-07-23; amendment status reviewed 2026-10-12Verified Oct 12, 2026
Phase II was still proposed after comments closed September 25. The December meeting was tentative; recommended reservoir maps may be conceptual.
- TWDB adopts the 2027 State Water PlanTexas Water Development Board · 2026-07-23Verified Oct 12, 2026
Statewide 2030–2080 projections and recommended projects. Completion and facility allocations require project records.
- NVIDIA GB300 NVL72 reference: current whole-rack power specificationVerified Oct 22, 2026
October 22 check: up to 142 kW for the whole rack. The source ledger and PUE inputs keep their recorded dates.
- Machine Learning Fleet Efficiency: Analyzing and Optimizing Large-Scale Google TPU Systems with ML Productivity GoodputWongpanich et al., Google and Harvard / arXiv · 2025-04-20Verified Oct 25, 2026
Version 2, April 20, 2025 preprint. TPU scheduling, runtime, and program-efficiency measurements inform how to assess preserved work on another architecture.
- Introducing ML Productivity GoodputGoogle Cloud · 2024-04-11Verified Oct 25, 2026
April 11, 2024 technical account of scheduling, runtime progress, throughput, and recovery recommendations.
Supporting material
- Capacity conversion model ↗Formula-driven facility, IT, rack, network, utilization, and sensitivity workbook.
- Source ledger ↗Primary and secondary sources with claims, definitions, limitations, and provenance.
- Claim ledger ↗Load-bearing claims classified as observed, derived, scenario, or interpretation.
- Methodology appendix ↗Research contract, definitions, formulas, provenance, contradictions, and calculation checks.
- Sensitivity data ↗PUE-by-external-IT-overhead matrix for installed B300 GPU equivalents.